| Cart Total:
Case Study
  • Healthcare

Pocono Medical Center: Faster Lab Results Using Six Sigma and Lean

Publication:
ASQ.ORG
Date:
October 2006
Pages:
pp. 1-4
Author(s):
Hayes, Walter T.; Cerra, Carmine J.; Williams, Mary

Abstract

The Pocono Medical Center initiated a Six Sigma/Lean project to deliver blood test results to doctors earlier in the workday. Within about six weeks, the project team implemented a solution. Doctors began to receive blood test results by 6 a.m. for critical care patients and by 7 a.m. for all other patients. Project results also extend outside of the laboratory, contributing to a decrease in overall patient length of stay for the medical center.